Task constraint in MS Project

R

RichardP

Can any MS Project gurus out there help me with this one. I have a constraint
on a summary task (detailed design) that goes like this: No more than 25% of
the detailed design may be finished before the high level design is finished.
HLD is the only predecessor to detailed design.

I know how to use the lag feature to implement the situation where Task B
can start when Task A is 80% complete, but don't know how to do it for the
situation I've described above. Is there a way it can be done in MS Project?

Regards,

Richard
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top