R
Richard Millard
Hi,
I have projects where certain tasks must be performed after an initial task
is completed. I am trying to create a template that can estimate the total
time it will take to complete the multiple tasks.
For example, Task B must follow Task A and typically takes 30% of the time
taken to complete Task A. Is it possible to set up a task so that it can
derive its duration as a percentage of the duration of its predecessor (or
of another linked task)?
Task A -> Task B
- if the Task A duration is set to 10 hours, Task B would automatically
calculate to an expected duration of 3 hours.
Thanks,
Richard
I have projects where certain tasks must be performed after an initial task
is completed. I am trying to create a template that can estimate the total
time it will take to complete the multiple tasks.
For example, Task B must follow Task A and typically takes 30% of the time
taken to complete Task A. Is it possible to set up a task so that it can
derive its duration as a percentage of the duration of its predecessor (or
of another linked task)?
Task A -> Task B
- if the Task A duration is set to 10 hours, Task B would automatically
calculate to an expected duration of 3 hours.
Thanks,
Richard