I have sub-tasks that add up to 50 hours, which is the figure I entered in
the main task duration. However, when I add the sub-tasks, the duration on
the task changes to two days and the application will not allow me to edit
it. I have a standard schedule set up, and one resource (employee) assigned
to the task. Any suggestions are greatly appreciated!