Task Duration

L

Lanheron

How do I enter a task of duration automatically equal to the overall project
duration regardless of how much the length of the project varies as actual
information is entered or the project is edited?

Thanks!

Lanheron
 
B

Brian K - Project MVP

Lanheron said:
How do I enter a task of duration automatically equal to the overall
project
duration regardless of how much the length of the project varies as actual
information is entered or the project is edited?

Thanks!

Lanheron

Check out www.mvps.org/project Click the FAQ link and find the one about
Hammock tasks. This will get you what you want.
 