G
Gary
I have two tasks that are assigned to three resources. When I make changes
in the View, Resource Usage, to the percent allocated for each task I adjust
the two tasks to show 50%. So the total for that day is 100%. When I make
the changes the duration in the Task view changes. Even if I change it back
to the correct duration, the View, Resource Usage changes. How do I make
project stick with the correct duration.
MS Project Professional 2003
in the View, Resource Usage, to the percent allocated for each task I adjust
the two tasks to show 50%. So the total for that day is 100%. When I make
the changes the duration in the Task view changes. Even if I change it back
to the correct duration, the View, Resource Usage changes. How do I make
project stick with the correct duration.
MS Project Professional 2003