I have a one day task that starts at 8:00 am and ends at 5:00 pm, yet the
number in the duration column field shows as .86. When I change the duration
column field to 1 day, it makes the end time 9:09 am the next day. If I try
to load 8 hours for a resource in this task (the task is a fixed work type
task), it says that the resource is over allocated. Can you tell me what
might be causing this?
number in the duration column field shows as .86. When I change the duration
column field to 1 day, it makes the end time 9:09 am the next day. If I try
to load 8 hours for a resource in this task (the task is a fixed work type
task), it says that the resource is over allocated. Can you tell me what
might be causing this?