Hi all,
Usinf MSP'98.
I want to have a task which is spread across full project & ver
independant. Meaning it will have start date as project start date
end date as project end date.
It will have work indicated in hours which are also equally spread ove
the entire duration of the project.
I will create a macro which will update its %completion & %wor
completion equal to that of ActiveProject.
But how to define such a task ?
Thanks in advance