R
Rick King
I am new to project 2007 and am having some issues with resource leveling. I
am NOT using project server but do have a resource Pool set up that I am
using for a few projects.
The issue I am having is when I try and scheule a task that takes more hours
then there are in a single day ie 10 hours, and I level resouces it will push
the start date out to the first day where that resource has no other tasks
assigned.
example
resource has been allocated 2 hours of work per day on Monday-Thursday. I
then have a 10 hour task I want to assign the resource. I would like it it
automatically look at the availablilty and assign 6 hours of the task on
Monday and the remaining 4 on the Tuesday.
What is acutally happening is it wont start the task until Friday where will
will allocate 8 hours and then 2 hours on the following Monday. How can I get
project to recognize and use the 6 hours of available time on Monday-Thursday?
am NOT using project server but do have a resource Pool set up that I am
using for a few projects.
The issue I am having is when I try and scheule a task that takes more hours
then there are in a single day ie 10 hours, and I level resouces it will push
the start date out to the first day where that resource has no other tasks
assigned.
example
resource has been allocated 2 hours of work per day on Monday-Thursday. I
then have a 10 hour task I want to assign the resource. I would like it it
automatically look at the availablilty and assign 6 hours of the task on
Monday and the remaining 4 on the Tuesday.
What is acutally happening is it wont start the task until Friday where will
will allocate 8 hours and then 2 hours on the following Monday. How can I get
project to recognize and use the 6 hours of available time on Monday-Thursday?