Task must finish on the same date as a predecessor

M

Mary

How do you link a task to complete on the same date (i.e. set as a deadline)
as another task in order to clearly show the dependency vs. a constraint
deadline date (e.g. the end date of the predecessor may shift, but that
should also generate a shift in the successor.)
 
G

Gérard Ducouret

Mary,

Use a Finish-Finish like (FF)
For example, if the predecessor is on the row #10 : 10FF
Hope this helps,

Gérard Ducouret
 
J

Jan De Messemaeker

Hi,

Link the tasks
In the successor Task Information, Predecessors pad
Change dependency type to Finish to Finish

HTH
 