Task sheet and actuals Q.

A

AndyB

Hi,

I am entering actual work in hours as recorded in resource timesheets in the
task sheet/work view.

Is there a way to get the %complete from the task sheet to update the
%complete in the normal gantt view to maintain conformity in both views?

Thanks,

AndyB.
 
J

Jan De Messemaeker

Hi Andy,

If it's really %complete you watch, they are conform in all views.
But I'm iunder the impression that you watch %work complete in one view and
%complete in the other.
They may be different since %w.C. = actual Work/work and %complete=Actual
Duration / Duration.
HTH
 
A

AndyB

Thanks Jan,

I understand now, they are totally different. I'll have a re-think of the
problem.
Thanks again,

Andy
 