Task Sheet View -

M

Mark Byington

I can add baseline start and baseline finish to the PWA Task Sheet View...but
no values appear. Anyway to make these fields populated?

Thanks
 
M

Mark Byington

Thanks, Dale.

It worked for Baseline Start, but Baseline Finish remained blank..(??).

Also, it seems to me that the field will only be populated on a project by
project basis IF the PM adds the field to their projects. So, the fields
will be sort of a nuisance for those that don't use it. Seems like I should
get consensus that this is data they want to see in the task sheet view,
before making the change in the production environment.

Thanks...
 
D

Dale Howard [MVP]

Mark --

Your project managers must do all the steps detailed in the FAQ. Adding
Published Fields is done on a project by project basis, as is the
republishing of assignments. Hope this helps.
 