R
russellmcox
My Project begins 2 months ago.
I have tasks that could have started prior to todays date and have slack time.
Because the task constraints default to ASAP, they currently show the start
dates that in theory could have been the actual start dates that are earlier
than today's date. But, since they were not started they cannot start prior
to todays date. I understand the situation, but people who are looking at the
gantt schedule do not.
I do not want to set the task constraint to ALAP, because this would obscure
the available slack time.
Is there any way to get tasks that have not started to show a "possible"
start date equal to the current date?
I know I could set the task constraints to "Start No Sooner Than...", but
that would require changing every task every day I (or someone elase) looks
at the project.
TIA,
Russell Cox
I have tasks that could have started prior to todays date and have slack time.
Because the task constraints default to ASAP, they currently show the start
dates that in theory could have been the actual start dates that are earlier
than today's date. But, since they were not started they cannot start prior
to todays date. I understand the situation, but people who are looking at the
gantt schedule do not.
I do not want to set the task constraint to ALAP, because this would obscure
the available slack time.
Is there any way to get tasks that have not started to show a "possible"
start date equal to the current date?
I know I could set the task constraints to "Start No Sooner Than...", but
that would require changing every task every day I (or someone elase) looks
at the project.
TIA,
Russell Cox