Task Time (Duration)

  • Thread starter Oh-its-all-gone-wrong
  • Start date
O

Oh-its-all-gone-wrong

Hi All,

Hope somebody could help a newbie out? Is there a way to change the task
time on MS Project to be Minutes or Hours rather than days?

Many Thanks
Si
 
D

DeJan

Hi,

Tools, Options, Schedule allows you to select what you need.
HTH



Oh-its-all-gone-wrong schreef:
 
J

JulieS

Hi Oh...,

In addition to Jan's suggestion, you may also wish to run the
Format_Duration macro to change the duration of tasks you have already
entered. Go to Tools>Macro>Macros, select the Format_Duration macro,
click the Run button and select Hours or Minutes.

You may also like to change the format of the start and finish dates to
show time as well as date. Go to Tools > Options, view tab and select a
format showing date and time.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 