I am facing a problem of task duration changing while
team members report their actual work done on a daily
basis.
Which is the best method of setting task type: Fixed
Units, Fixed Duration & Fixed Work. What is the
difference? Where can this be set on the Project Server to
control all Projects? In the PWA Admin, I can only find
reporting progress,Time period settings?
Should tasks be set to effort driven or not?
Regards,
David