D
David M C
Just a couple of questions.
What is the most common task type? Project seems to default to Fixed Units
but I would have thought (for effort driven tasks) fixed work was more
reflective of the real world. Surely, any given task has a fixed amount of
work that needs to be done? Examples of when you might use each type would be
appreciated.
Secondly, a bit more specific. I have a task that requires 48h of work. This
is a 6 day task with one resource assigned at 100%. However, I would now like
to shorten the duration of this task by 1 day, by assigning another resource,
at 100% for 1 day (ie, one resource does 40h work, the other does 8h). How
would I do this?
Thanks
Dave
What is the most common task type? Project seems to default to Fixed Units
but I would have thought (for effort driven tasks) fixed work was more
reflective of the real world. Surely, any given task has a fixed amount of
work that needs to be done? Examples of when you might use each type would be
appreciated.
Secondly, a bit more specific. I have a task that requires 48h of work. This
is a 6 day task with one resource assigned at 100%. However, I would now like
to shorten the duration of this task by 1 day, by assigning another resource,
at 100% for 1 day (ie, one resource does 40h work, the other does 8h). How
would I do this?
Thanks
Dave