V
Vikramramdev
I have a project Plan, where we have set the Start Date & Times,.
Not ,. we have released the tasks to all the task owners,..
Say for example we have a Task " Extract all Purchase Orders" 10/13/08,. 10.AM
Now my question is:
What if we get a status update from the task owner saying that the task was
done on 10/7 9.0AM. How are we updating this,.. in the plan,..
If i change in the Plan directly,.. the dates gets disturbed , like it
pushed the date forward or backward,..
We are only capturing the Actuals for the main plan,. based on the actuals,.
So i appreciate your answers with a detailed explanation.
Thanks
Vikram.
Not ,. we have released the tasks to all the task owners,..
Say for example we have a Task " Extract all Purchase Orders" 10/13/08,. 10.AM
Now my question is:
What if we get a status update from the task owner saying that the task was
done on 10/7 9.0AM. How are we updating this,.. in the plan,..
If i change in the Plan directly,.. the dates gets disturbed , like it
pushed the date forward or backward,..
We are only capturing the Actuals for the main plan,. based on the actuals,.
So i appreciate your answers with a detailed explanation.
Thanks
Vikram.