S
Sriram
Hi,
How can a team member indicate, they have finished a task
ahead of time & task is 100 % done, even though remaining
hours avbl. How to apply different costs ( from cost
table of a resource) for different tasks of a resource in
the same projects ?
Also, How does the Team Member update the NonProjectTime
Category ?
Regards
Sriram
How can a team member indicate, they have finished a task
ahead of time & task is 100 % done, even though remaining
hours avbl. How to apply different costs ( from cost
table of a resource) for different tasks of a resource in
the same projects ?
Also, How does the Team Member update the NonProjectTime
Category ?
Regards
Sriram