Task Update

S

Sriram

Hi,

How can a team member indicate, they have finished a task
ahead of time & task is 100 % done, even though remaining
hours avbl. How to apply different costs ( from cost
table of a resource) for different tasks of a resource in
the same projects ?

Also, How does the Team Member update the NonProjectTime
Category ?

Regards

Sriram
 
K

Kevin Flanagan

If the task is complete, the resource needs to put zero
in the remaining hours.

To apply a different cost table to a resource you must
first be in either the Task Usage view or the Resource
Usage view. Usign the Assignment Information dialog box
is probably the easiest way to assign. Choose one of the
lettered cost tables in the drop-down list in the Cost
Rate Table field to assign that cost table's std, OT, and
per-use rates to he assignment. Cost Rate tables can
only be edited in the Resource Information dialog box.

First you need to define the non-working time categories
and when chosing the timesheet view, the resource will
have boxes in which to enter their time. They may have
to scroll to find the entry boxes depnding on their
screen resolution.
 
S

Sriram

Hi,

Thanks for the help.

I have set " Actual work done and work remaining:
Resources report the actual work done and the work
remaining to be done on each task " option in Tracking
setting under Customize Microsoft Project Web Access Menu.
But, i am able to update only Actual Work but Remaining
Work is non-editbale.

So i need do any otehr setting to enable both ACt &
Remaining Work ? If Rem Work is set more .. will the
planned work for the task increase ?

Thanks again.

Regards

Sriram
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top