B
Barb Van Horn
I am sure this is some funny quirk of Project that I just
haven't figure out yet, but I can't seem to get the
duration to fit the hours when I have multiple resources
assigned to a single task.
The example task is 40 hours which is neatly divisible by
8 hours (our working day). This is a fixed work task with
2 resources. When I split them 50/50 it is a nice round 5
days. When I split them 60/40, it goes up to 6.25 days.
Can anyone explain why? And can someone tell me how to
correctly split this up so that it still takes 5 days but
relects that resource 1 will do more of the work?
Thanks in advance for the assistance.
haven't figure out yet, but I can't seem to get the
duration to fit the hours when I have multiple resources
assigned to a single task.
The example task is 40 hours which is neatly divisible by
8 hours (our working day). This is a fixed work task with
2 resources. When I split them 50/50 it is a nice round 5
days. When I split them 60/40, it goes up to 6.25 days.
Can anyone explain why? And can someone tell me how to
correctly split this up so that it still takes 5 days but
relects that resource 1 will do more of the work?
Thanks in advance for the assistance.