Task wont both start Saturday an finish following Sunday, Project

S

Sammy1973

I cant seem to figure out how to make a 9 day task start on Saturday and then
finish on the following Sunday, does not seem to want to count the weekends
as working days. Calendar is setup for 24 hour day/
 
J

JulieS

Hello Sammy,

A couple of questions:
Are you using the "24-hours" calendar that comes with Project or a
custom calendar you created?
Have you set the calendar as the Project calendar in Project > Project
information?
Do you have resources assigned to the task?
What is the resource's base calendar?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 