D
dran
Hi,
We got project server 2003 with SP2a.
Situation is as follows:
- user enters actual work on tasks page,
- user clicks save button for entered actuals,
- user DOES NOT click update all button.
- manager can see and accept enterd actuals despite udate all button was not
pressed.
- It does not happen for all users, I found it happens for one person,
- For this person I tried to enter protected actuals for different task
(from the same schedule) and clicked save changes again button update all
was not clicked.
Manager could not see entered actuals so it was OK.
- It happens for task with already reported and saved and updated actuals.
New actuals are set for approval to manager without update all button.
Any ideas?
Regards,
Jakub
We got project server 2003 with SP2a.
Situation is as follows:
- user enters actual work on tasks page,
- user clicks save button for entered actuals,
- user DOES NOT click update all button.
- manager can see and accept enterd actuals despite udate all button was not
pressed.
- It does not happen for all users, I found it happens for one person,
- For this person I tried to enter protected actuals for different task
(from the same schedule) and clicked save changes again button update all
was not clicked.
Manager could not see entered actuals so it was OK.
- It happens for task with already reported and saved and updated actuals.
New actuals are set for approval to manager without update all button.
Any ideas?
Regards,
Jakub