Tasks being set as milestones

B

Betsy

I have a project that has a lot of tasks that are set with durations but with
0 hours. These tasks are set to fixed duration. When I save the plan,
Project 2003 sets these tasks as milestones. How can I keep this from
happening?
 
J

JulieS

Hi Betsy,

I'm not sure I follow your scenario exactly. When you say the tasks are
"set with durations but with zero hours" -- what is zero hours? The work?
By default in Project, tasks with zero *duration* are milestone tasks, but
tasks with any duration other than zero are not.

Julie
 
J

Jan De Messemaeker

Hi,

Insert the column "Milestone" and put to No where you need it.
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top