ArnoS
Ik cannot find the cause of this problem.
In FS dependencies the tasks end the next day. The day where the successors
start.
eg. task 1 has a duration of 1 day. It starts on monday and ends on tuesday.
Where its successor starts on tuesday and ends on wednesday. I prefer that a
one day task starts and ends on monday, while its successor starts and ends
on tuesday.
Because I have copied tasks from other files I also have some tasks who
behave as I want them.
Another symptom that has something to do with this, is the duration of a
summary task having an offset of 0.06 day (too much or too little).
I have asked around, but no luck yet. Anyone who knows how to tackle this?
In FS dependencies the tasks end the next day. The day where the successors
start.
eg. task 1 has a duration of 1 day. It starts on monday and ends on tuesday.
Where its successor starts on tuesday and ends on wednesday. I prefer that a
one day task starts and ends on monday, while its successor starts and ends
on tuesday.
Because I have copied tasks from other files I also have some tasks who
behave as I want them.
Another symptom that has something to do with this, is the duration of a
summary task having an offset of 0.06 day (too much or too little).
I have asked around, but no luck yet. Anyone who knows how to tackle this?