Tasks linked but not repsonding to changes without both being open

  • Thread starter % Complete vs Actual Work
  • Start date
%

% Complete vs Actual Work

At this point I have linked a task from a subproject to a master project. I
did this by copying the link and paste special, link. Work great and easy to
do. However in order to see the changes in the master that I make in the
subproject I have to have them both open. I am using MS PRoject 2007 and
Project Server 2007. I would appreciate any thoughts to this!
 
J

John

% Complete vs Actual Work
At this point I have linked a task from a subproject to a master project. I
did this by copying the link and paste special, link. Work great and easy to
do. However in order to see the changes in the master that I make in the
subproject I have to have them both open. I am using MS PRoject 2007 and
Project Server 2007. I would appreciate any thoughts to this!

Person,
Well the first problem is that you used paste links. Paste links may be
"easy" to create and seem like a really nifty approach but they are very
fragile and easily corruptible. What you should be using are external
predecessors. You can read more about those in the Project help file.

John