% Complete vs Actual Work
At this point I have linked a task from a subproject to a master project. I
did this by copying the link and paste special, link. Work great and easy to
do. However in order to see the changes in the master that I make in the
subproject I have to have them both open. I am using MS PRoject 2007 and
Project Server 2007. I would appreciate any thoughts to this!
did this by copying the link and paste special, link. Work great and easy to
do. However in order to see the changes in the master that I make in the
subproject I have to have them both open. I am using MS PRoject 2007 and
Project Server 2007. I would appreciate any thoughts to this!