I am sure this is a totally simple fix but…..
I have a task that is linked to another. The first take is a one day
duration (8a to 5 p). The second task is also one day but is shown to start
at 5 p on the first day. The first task was finishing on the same minute as
the second was starting. The second task should start at 8 a on the second
day.
Yes I checked the calendar and the hours per day……
I have a task that is linked to another. The first take is a one day
duration (8a to 5 p). The second task is also one day but is shown to start
at 5 p on the first day. The first task was finishing on the same minute as
the second was starting. The second task should start at 8 a on the second
day.
Yes I checked the calendar and the hours per day……