Hi, I'm new to Project and apologise if this is a stupid question.
I've got Project 2002 if it makes any difference.
I have two tasks which can happen any time within my project except at the
same time as each other. They are both assigned the same resource. Only 1
person can do each task at any one time, and there are two people available
to do the task. This means that when I level the tasks they get assigned to
be done at the same time as each other. How do I constrain them so that they
do not happen together without saying that one has to be done before the
other, because I don't know which way round is best for the system?
Thanks
Helen
I've got Project 2002 if it makes any difference.
I have two tasks which can happen any time within my project except at the
same time as each other. They are both assigned the same resource. Only 1
person can do each task at any one time, and there are two people available
to do the task. This means that when I level the tasks they get assigned to
be done at the same time as each other. How do I constrain them so that they
do not happen together without saying that one has to be done before the
other, because I don't know which way round is best for the system?