Text Fields in Resource View

C

Chama

The text fields I have inserted and renamed in the Gantt Chart view don't
carry over to the Resource View.

I want to put different charge numbers against each task and I want to see
that charge number when I change to the Resource View.

Any ideas?
 
J

JulieS

Hello Chama,

As you have discovered, tasks (Gantt chart view) and Resources each
have a set of custom fields and a data entered into one side, does not
display in the other field.

See FAQs 37 & 51 at http://project.mvps.org/faqs.htm for some
additional information. FAQ # 37 also has two sample macros to copy
data from one field to another.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 