The Following Tasks need updates.

R

Ryan

"The Following Tasks need progress updates."

This message is sent in email notification from project web access.

What is this referring to? And how is it generated?

Ryan
 
D

Dale Howard [MVP]

Ryan --

This message means that your project manager selected the task(s) in
Microsoft Project Professional and requested an interim progress update. In
response, you should navigate to your PWA timesheet, enter progress on the
task(s), and then update your project manager. Hope this helps.
 
Top