Time Schedule Variance

L

Luke Ulrych

I was wondering if there was a way to assign hours to a task, but vary it by
week. For example if someone is working on a testing phase and in one week
they will work on it for 10 hours, but the next couple of weeks they will
work on it for 20 hours. Do you have to seperate these and assign two
different tasks or can it be done on one task.

Thanks for your help.
 
J

Jan De Messemaeker

Hi Luke,

It can be done on one task; work can be contoured using the task usage view.
Mind you, should the tak be delayed, the contour gets delayed, which means
that the 10-20 etc. now may well fall another week.
HTH
 