Timesheet entry for Admin Projects

B

Bill

MS Project seems to add actual work at the rate of planned work for blank
cells of PWA Timesheet entries. The added actial work only shows up in
Project. It does not add these hours to the Team Members PWA Tasksheet.
Normal project files seem to fill in the blank gaps with 0's.
Is this normal ?
How can stop project from adding actual hours to Admin tasks when the
timesheet has blank cells ?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top