S
Sriram
Hi,
How to set Timesheet update, to allow resource to edit
both Act hours or remaining hours for a task, so the
resource can specify either Task is completed ahead of
schduel by giving Remaining hours Zero or increacsing to
indicating the task is getting more time than plan ?
Any inputs welcome.
Regards
Sriram
How to set Timesheet update, to allow resource to edit
both Act hours or remaining hours for a task, so the
resource can specify either Task is completed ahead of
schduel by giving Remaining hours Zero or increacsing to
indicating the task is getting more time than plan ?
Any inputs welcome.
Regards
Sriram