M
Michele
First of all, nice to meet u all.
I have a project scheduled from the start date.
I have a number of tasks that generate a critical path.
I create another task called, just for example, "y", with no relationship
with any of the other tasks but with the constraint equal to "As late as
possible".(The duration of the project is anyway longer than the duration of
the single "y" task)
It's correct and my logic accept the fact that microsoft project indicates
me that the task "y" is critical.
But the problem is:
I set for the task "y" an actual start date that is earlier than that one
programmed by project at the beginning using the constraint "As late as
possible".(But not earlier than the start date of the project)
I would expect that project indicated me that "y" task was not anymore a
critical task.
What i mean is that if I start a task before than its last possible beginning
it's clear for me that i can delay that activity for a certain amount of
time withouth delaying the date of the end of the project.
If i change the constraint for "Y" task to "As soon as possible" things
work logically and the amount of total slack is greater than 0 but if leave
"As late as possible" i have total slack that is equal to 0.
Thanks in advice for helping me in understanding where i am wrong.
Michele
I have a project scheduled from the start date.
I have a number of tasks that generate a critical path.
I create another task called, just for example, "y", with no relationship
with any of the other tasks but with the constraint equal to "As late as
possible".(The duration of the project is anyway longer than the duration of
the single "y" task)
It's correct and my logic accept the fact that microsoft project indicates
me that the task "y" is critical.
But the problem is:
I set for the task "y" an actual start date that is earlier than that one
programmed by project at the beginning using the constraint "As late as
possible".(But not earlier than the start date of the project)
I would expect that project indicated me that "y" task was not anymore a
critical task.
What i mean is that if I start a task before than its last possible beginning
it's clear for me that i can delay that activity for a certain amount of
time withouth delaying the date of the end of the project.
If i change the constraint for "Y" task to "As soon as possible" things
work logically and the amount of total slack is greater than 0 but if leave
"As late as possible" i have total slack that is equal to 0.
Thanks in advice for helping me in understanding where i am wrong.
Michele