The summary bars by default show the MAXIMUM amount of Slack of the subordinate tasks. This is useless to a scheduler, you need to show MINUMUM slack as this will show you where problem areas are.
Until I find how to change this setting, I set a custom duration field to equal the Finish Slack and tell it to show minimum on the summary bar.
Insert a new column: duration1.
Right Click on duration1 column, Customize Fields
Select Duration1 Formulae - OK to resetting it
Insert Field Duration Finish Slack
Rollup, Minimum - OK
Jack Dahlgren wrote:
Re: Total Slack on Summary Bars
05-May-08
The calculation for slack is
Total Slack = Late Finish - Early Finis
which is exactly the same as what G?rard said in words
-Jack Dahlgren
Previous Posts In This Thread:
Total Slack on Summary Bars
I have been asked by a program manager how total slack is calculated o
summary bars using Project 2003. I have looked thru Project books but do no
see the answer anywhere
-
bmartin
Betsy,Like its subordinate elementary tasks, the total slack of a summary is
Betsy
Like its subordinate elementary tasks, the total slack of a summary is the
amount of time the summary can drift without postponing the finish date of
the project
G?rard Ducoure
"Betsy" <
[email protected]> a ?crit dans le message de (e-mail address removed)...
Re: Total Slack on Summary Bars
The calculation for slack is
Total Slack = Late Finish - Early Finis
which is exactly the same as what G?rard said in words
-Jack Dahlgren
EggHeadCafe - Software Developer Portal of Choice
How to do a Vista?Over?Vista Upgrade Repair
http://www.eggheadcafe.com/tutorial...3cf-2c341aed7c08/how-to-do-a-vistaovervi.aspx