Totalling Resources as a Percentage

S

SBakerNYC

I need to create a management level summary containing total resources needed
by hour by week. The current plan has eash individual resource listed and I
haven't located any formula or filter option where I can total these
resources.

Thank you.
 
J

Jan De Messemaeker

When in the task usage view, Tools, Options, View, show project summary
task.
HTH
 