Zoomnbyu
Embarrassingly stuck because I'm sure this is easy and I'm just having a
brain cramp. How do you have Project track functional time vs calendar time
at the task level? For example, I have a task that starts 2/1/08 and ends
3/1/08 but will really only involve about 40 hours of the analysts time. How
do I get Project to recognize the 40 hours versus the calendar hours but
still show the correct start and finish dates.
Thanks for the help.