Track functional time versus calendar time

Z

Zoomnbyu

Embarrassingly stuck because I'm sure this is easy and I'm just having a
brain cramp. How do you have Project track functional time vs calendar time
at the task level? For example, I have a task that starts 2/1/08 and ends
3/1/08 but will really only involve about 40 hours of the analysts time. How
do I get Project to recognize the 40 hours versus the calendar hours but
still show the correct start and finish dates.

Thanks for the help.
 
G

Gérard Ducouret

Hello,
i'm afraid you are confusing Duration and Work.
Did you assign the Analyst resource on that task?
40h of Work spread over a Duration of 21 days = assignment at 27%
Display the Work column (and/or the Actual Work) in any table or in the Task
Usage view

Hope this helps
 