D
Deb's Project's questions
Hello,
A brief description of the project.
The project that I am working on is quite basic but causing me grief.
My project consists of approx. 10 tasks all starting on the same day, and
finishing on the same day. Some resources may be assigned to one or more
tasks. The duration of tasks can range from 30 minutes to usually not more
than 5 days.
First of all our work day is 8:30 - 4:30, 1 hr for lunch. I thought that I
had changed the calendar to be 8:30 to 4:30, but the Gnatt chart is still
starting at 8:00 am.
We also work a 7 hour day and a 35 hour week.
It seems that the best way to tract this project on the Gnatt chart is to
use the timescale by hours. If I use the timescale by days the task bar for
a 30 minute task is very small. I also am having some difficulty when I set
the % complete on a task to 50%, it basically runs across the entire bar, not
just halfway through.
Microsoft Project 2003
I hope that you can help me.
Thank you very much.
A brief description of the project.
The project that I am working on is quite basic but causing me grief.
My project consists of approx. 10 tasks all starting on the same day, and
finishing on the same day. Some resources may be assigned to one or more
tasks. The duration of tasks can range from 30 minutes to usually not more
than 5 days.
First of all our work day is 8:30 - 4:30, 1 hr for lunch. I thought that I
had changed the calendar to be 8:30 to 4:30, but the Gnatt chart is still
starting at 8:00 am.
We also work a 7 hour day and a 35 hour week.
It seems that the best way to tract this project on the Gnatt chart is to
use the timescale by hours. If I use the timescale by days the task bar for
a 30 minute task is very small. I also am having some difficulty when I set
the % complete on a task to 50%, it basically runs across the entire bar, not
just halfway through.
Microsoft Project 2003
I hope that you can help me.
Thank you very much.