C
College Student Learning Project
Is it possible to track changes to the schedule and make it easy to present
to customers? I would like to be able to overlap changes on top of the
baseline. Either a different color bar or different pattern for the portion
of the task that last longer than the original baseline.
For example: A task starting 6/1/06 with a duration of 3 days would be due
6/5/06 but scrapped material actually makes it deliverable on 6/8. I would
like the task bar to be blue from 6/1 until 6/5 then be red signifying that
it is edited or late.
Anyone know if this is possible? Even if it had to be a more manual
modification.
Thanks,
to customers? I would like to be able to overlap changes on top of the
baseline. Either a different color bar or different pattern for the portion
of the task that last longer than the original baseline.
For example: A task starting 6/1/06 with a duration of 3 days would be due
6/5/06 but scrapped material actually makes it deliverable on 6/8. I would
like the task bar to be blue from 6/1 until 6/5 then be red signifying that
it is edited or late.
Anyone know if this is possible? Even if it had to be a more manual
modification.
Thanks,