Tracking Gantt Problem

D

DC James

I have several tasks linked together with the first task beginning 4/15/07
and the finish date for the last task is mid October/07. However, if I
attempt to delay the start date on the first task (say 6/15) which pushes the
end date beyond 11/1/07, the progress bars on the right side of the Gantt
chart, disappear. Seems like some sort of conditional formating but I can't
find it.
 
G

Gérard Ducouret

Hello,
Why do you delay the start date on the first task while you entered some
actual data on its successors ?
Procede in the reverse order.

Gérard Ducouret
 
J

Jan De Messemaeker

Hi,

There must be some misunderstanding here.
Progress bars? Do you mean you have had some actual work on the tasks?
When there's been actual work in principle you should not delay the start.
But even then the propgress bar doesn't disappear.

Or are you talking about baseline bars? They will stay put and hence may get
out of sight.

By all means you can send me the file so I can have a look:
jandemes at prom-ade dot be

Hope this helps,
 