A
andre
I have been tasked with making a progress report showing percentage complete.
I have grouped the tasks into subtasks but left the duration at 1d? It's just
that the percent complete isn't accurate. I have a task of say lighting. It
has 2 subtasks of isntallation and hook-up, each of these worth 50% of the
total task. The problem arrises, I think, because the two items take
different amounts of time to complete and since I am not entering work
complete to get the percent and just entering the percentage it is throwing
off the calculation.
Any ideas on how to complete this report?
Oh and is there a way to upload the file so anyone can see it?
I have grouped the tasks into subtasks but left the duration at 1d? It's just
that the percent complete isn't accurate. I have a task of say lighting. It
has 2 subtasks of isntallation and hook-up, each of these worth 50% of the
total task. The problem arrises, I think, because the two items take
different amounts of time to complete and since I am not entering work
complete to get the percent and just entering the percentage it is throwing
off the calculation.
Any ideas on how to complete this report?
Oh and is there a way to upload the file so anyone can see it?