T
tgr
My question pertains to tracking schedules for tasks that can be worked on
out of order. Here’s the setup:
A person has several tasks assigned to him, all which must be completed by
the end of the project. I link them together in this order: A->B->C. Due to
the nature of the work, he might work first on task A for a day, then on task
B for a couple of days, then task A for a few more days, then task C for a
few days. Then, he’ll go back to task B and finish it, before going to
finish task A, etc. The point is the tasks can be worked on in an order
different than the way they are linked. They may be worked on before or
after they are scheduled. They are linked as A->B->C because that is the
“generally accepted order one could expect to followâ€, but our process is
very flexible on an individual basis. (This is software development as you
might guess.)
I’d like to be able to track progress of this project and understand if it
is on schedule. Any suggestions on how to do this correctly?
out of order. Here’s the setup:
A person has several tasks assigned to him, all which must be completed by
the end of the project. I link them together in this order: A->B->C. Due to
the nature of the work, he might work first on task A for a day, then on task
B for a couple of days, then task A for a few more days, then task C for a
few days. Then, he’ll go back to task B and finish it, before going to
finish task A, etc. The point is the tasks can be worked on in an order
different than the way they are linked. They may be worked on before or
after they are scheduled. They are linked as A->B->C because that is the
“generally accepted order one could expect to followâ€, but our process is
very flexible on an individual basis. (This is software development as you
might guess.)
I’d like to be able to track progress of this project and understand if it
is on schedule. Any suggestions on how to do this correctly?