Tracking tasks with multiple recources

S

Shurick

I have 2 resources for 1 task. One of resource is user, but another is not.
For example:
Task - "Show presentation"
Resources - Peter and "show room"
So, Peter show presentation and update status of assignment.
In project tracking i see that task is in 50% done, but must in 100%!
"show room" resource can not to report progress
 
D

Dale Howard [MVP]

Shurick --

You must manually update the % Complete for the show room resource in the
actual Microsoft Project plan. Hope this helps.
 
S

Shurick

Can i configure server to do that without human help?
I wrote just example, but in enterprise conditions is not possible to track
every task manualy!
 
R

Reid McTaggart

If it is not possible to track such detail, then perhaps you should consider
whether or not it makes sense to plan at that level of detail.
--
Reid McTaggart
EPM Architect
Microsoft
 