Hello everyone!! I am hoping someone can help me answer this question.
I have a resource pool which is linked to several projects. When I look at
the resource usage, under the work column, I have total number of hours
scheduled for each resources. That hours may be laid for a period of time
such as three month, one year or two years. I was wondering whether will I be
able to find the scheduled hours for a given time period, say from May 10,
2005 to February 11, 2006. Like I need to have two columns, one start date
and the other as end date. When I enter the start and end date I want the
number of scheduled hours during that period. I am not sure whether this can
be done or let me know if I am expecting more that what I should. I also
welcome any other method to achieve this. Any help really appreciated.
KT
I have a resource pool which is linked to several projects. When I look at
the resource usage, under the work column, I have total number of hours
scheduled for each resources. That hours may be laid for a period of time
such as three month, one year or two years. I was wondering whether will I be
able to find the scheduled hours for a given time period, say from May 10,
2005 to February 11, 2006. Like I need to have two columns, one start date
and the other as end date. When I enter the start and end date I want the
number of scheduled hours during that period. I am not sure whether this can
be done or let me know if I am expecting more that what I should. I also
welcome any other method to achieve this. Any help really appreciated.
KT