I need help! I have a project file in which I have two identical (as near as
I can tell) tasks, assigned the same resources, both fixed duration
effort-driven, and I get two different cost calculations on the Gantt chart.
What could be the cause of that? Again, I've checked everything in the Task
Information dialogue and all appears to be identically configured yet one
task's cost is way off. Any thoughts?