Unallocated Resource

F

Feeon

I'm new to project and I was wondering if it is possible to indicate the
number of mandays per week required from a specific resource type for the
duration of the project where the resource remains unallocated (i.e. where
resource is not available). I'm using Project 2003

Thanks
 
J

Jan De Messemaeker

Hi,

There are several solutions here, and recently in a thread it has been shown
that each method has strong supporters. I'll try to give them unbiased:

- You declare some time in the resource's calendar as nonworking time, f.i.
for a resource that is vailable 3 days a week, you put Tue and Thu as
nonworking time
- Or in the resoruce sheet you put the Max Units for the resource to 60% (in
this example)
- Or (insofar you use resoruce leveling) you create a recurring task to
which the resource "works" two days each week

It would take me too long to explain pros and cons of each method, try and
see.

HTH
 
F

Feeon

Hi Jan

Thanks alot for all your help you have helped me to understand the way
Project uses resources.
 