D
DDDDDD
i am not sure about naming my subject as underallocation.
i have task = 3h work
it is fixed work
also, only 1 resource is allocated for it
the allocation unit is 100%
and the plan is distributing this work between 2 days as 1.5 h in one day
and 1.5 in the following day.
also, there is no other task assigned in this day to my resource and working
hours are 6.5 h/day
my 1st question is why do the MS project distributed like this instead of
putting the whole 3 h in one day??
the 2nd question when i change the unit of this resource to 200% it is
marked red as overallocated, why is this happening?
please, advise.
thanks,
ddd....
i have task = 3h work
it is fixed work
also, only 1 resource is allocated for it
the allocation unit is 100%
and the plan is distributing this work between 2 days as 1.5 h in one day
and 1.5 in the following day.
also, there is no other task assigned in this day to my resource and working
hours are 6.5 h/day
my 1st question is why do the MS project distributed like this instead of
putting the whole 3 h in one day??
the 2nd question when i change the unit of this resource to 200% it is
marked red as overallocated, why is this happening?
please, advise.
thanks,
ddd....