Undividable activity

N

natash@

I have many activities done by one people. When I short of stuff, project
divides activities. So, if there are not enough people I would prefer
starting activities later, but to leave them undividable. Where can I define
activities undividable (have to be done in one step).
Thanks a lot if someone can answer.
Best regards, Natasha
 
J

Jim Aksel

Tools/Options/Schedule Tab deselect "Split in Progress tasks"
Tools/Options/Calculations tab deselect the two boxes that start "Move..."
Tools/Level Resources.... deselect "Leveling can create splits in
remaining work"

You may need to clear leveling. You should have Resource Leveling set to
manual.

If this post helps, please consider rating it.

Jim
 