Unidentified seperator in Project

B

Brian

A sample project plan that I'm viewing has a horizontal dashed line as a
seperator between summary tasks while viewing the Cantt Chart. The task not
in ID order. I can't figure out how to turn on/off the dashed lines or to
replicate this view.
 
J

John

Brian said:
A sample project plan that I'm viewing has a horizontal dashed line as a
seperator between summary tasks while viewing the Cantt Chart. The task not
in ID order. I can't figure out how to turn on/off the dashed lines or to
replicate this view.

Brian,
As a quick guess, first I'd say the file is sorted or filtered. That
would explain the non-contiguous ID numbers. Re-sort by ID and/or apply
the "all tasks" filter. Second, the dashed horizontal lines are manual
page breaks. To remove, select the line below the dashed line and go to
Insert/Remove Page Break.

Hope this helps.
John
Project MVP
 
M

Mike Glen

Hi Brian,

Welcome to this Microsoft Project newsgroup :)

Sounds like a page nreak indicator. Select the task underneath the dotted
line and then Insert/Remove page break.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top