greggw3gs
I have two questions that are related.
First,I am having a problem with a task that needs to be accomplished in its
entirety and cannot be started one day and completed the next such as a
several hour test. How can I force such a task to only start when there is
sufficient time to completd it?
Second, How does one handle alternate resources on two shifts? I have two
technicians running tests one on the day shift, one on evenings. Test which
are run can be run by either depeding on when they occur. How do I show one
or the other resource being use to maximize flexibility?
Gregg Foster (greggw3gs)
First,I am having a problem with a task that needs to be accomplished in its
entirety and cannot be started one day and completed the next such as a
several hour test. How can I force such a task to only start when there is
sufficient time to completd it?
Second, How does one handle alternate resources on two shifts? I have two
technicians running tests one on the day shift, one on evenings. Test which
are run can be run by either depeding on when they occur. How do I show one
or the other resource being use to maximize flexibility?
Gregg Foster (greggw3gs)