update dates

K

KC

I'm updating an exsisting Project.

Why can't I change the start dates on the task.
The date drop down arrowis grey.
 
J

Jim Aksel

You cannot change the date of summary tasks. Instead, using predecessors and
durations the dates of the subordinate (indented) tasks may be changed.

Generally, it is not good to key a date into a task because it will create
constraints. For example, if you key in a start date, you will be creating a
Start No Earlier Than constraint. Not good, because if a predecessor task
finishes early, this task will not start until the date keyed.
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
A

AL

Hi Jim,
I'm facing the same Date (Start & End) field problem when creating new
tasks. I', running on PWA 2003 and terminal services. I keep getting ActiveX
control when reach Date field to press SPACEBAR/ENTER and return the system
dates for both Start and End. Our users want a Calender view to choose.
Please advise any solutions? Is urgent cos the training going to start soon
for the users.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top