You cannot change the date of summary tasks. Instead, using predecessors and
durations the dates of the subordinate (indented) tasks may be changed.
Generally, it is not good to key a date into a task because it will create
constraints. For example, if you key in a start date, you will be creating a
Start No Earlier Than constraint. Not good, because if a predecessor task
finishes early, this task will not start until the date keyed.
--
If this post was helpful, please consider rating it.
Jim