H
Harry Seymour
Hi,
I’m working on a programme plan managing several Projects (in Vista). I
need a Master programme plan has the projects inserted. I also want to
create dependencies between the projects.
However, when one of the projects update its timeline I need to ensure that
it does not immediately impact other project timelines (in the master or
other project plans). What I do want to happen is for the Master to show
that a change has been made, what that change is, but not immediately accept
it and adjust all other project plans.
This will allow the manager of the Master plan to review and understand
changes before they’re accepted, and also discuss and communicate changes to
the project plans.
Do you know how I can do this? It could be as simple as flashing a task red
(in the Master) when it has been changed in a Project plan then a simple
mechanism to ‘accept’ the change which would then feed the change into the
other plans.
thanks
Harry
I’m working on a programme plan managing several Projects (in Vista). I
need a Master programme plan has the projects inserted. I also want to
create dependencies between the projects.
However, when one of the projects update its timeline I need to ensure that
it does not immediately impact other project timelines (in the master or
other project plans). What I do want to happen is for the Master to show
that a change has been made, what that change is, but not immediately accept
it and adjust all other project plans.
This will allow the manager of the Master plan to review and understand
changes before they’re accepted, and also discuss and communicate changes to
the project plans.
Do you know how I can do this? It could be as simple as flashing a task red
(in the Master) when it has been changed in a Project plan then a simple
mechanism to ‘accept’ the change which would then feed the change into the
other plans.
thanks
Harry