A
aaren
Am tracking multiple projects for which there is a single resource
pool. The situation is like this. Project A, B, C and D are running
concurrently but A will close first, then B and so on. When proect
reaches its peak for about a week, the resources allocation will be
solely for Project A and for that week, many of the resources wont be
available for the other projects. Similarly, when project B is going
to close, the resources wont be available for other remaining projects.
What I have done is to go to the resource pool, and updated the key
resources availability as N.A during the week when a project is closing
down. But the problem is, during the week when am closing Project A
down, how do I get use these resources for Project A ??
Any thoughts ??
pool. The situation is like this. Project A, B, C and D are running
concurrently but A will close first, then B and so on. When proect
reaches its peak for about a week, the resources allocation will be
solely for Project A and for that week, many of the resources wont be
available for the other projects. Similarly, when project B is going
to close, the resources wont be available for other remaining projects.
What I have done is to go to the resource pool, and updated the key
resources availability as N.A during the week when a project is closing
down. But the problem is, during the week when am closing Project A
down, how do I get use these resources for Project A ??
Any thoughts ??